Which statement about risk mitigation and contingency planning is correct?

Prepare for your Project Implementation and Management Test with our comprehensive materials. Utilize flashcards and multiple choice questions, each with hints and explanations. Get ready to succeed!

Multiple Choice

Which statement about risk mitigation and contingency planning is correct?

Explanation:
Risk mitigation is about taking proactive steps to lower either the likelihood of a risk occurring or its impact. The statement that it involves developing and deploying a plan to avoid, transfer, share, and reduce project risk captures the full range of typical responses: avoidance (changing the plan to eliminate the risk), transfer (shifting the risk to another party), sharing (risk-sharing arrangements), and reduction (implementing controls to lessen the chance or effect). Contingency planning, by contrast, is about having predefined actions to take if a risk event occurs, not about avoiding the risk in advance. It prepares for risk events and their triggers rather than preventing the risk from happening. The other options misstate these ideas: contingency planning is related to risk events, risk mitigation is not limited to transferring risk, and avoidance of risk entirely isn’t the aim of contingency planning.

Risk mitigation is about taking proactive steps to lower either the likelihood of a risk occurring or its impact. The statement that it involves developing and deploying a plan to avoid, transfer, share, and reduce project risk captures the full range of typical responses: avoidance (changing the plan to eliminate the risk), transfer (shifting the risk to another party), sharing (risk-sharing arrangements), and reduction (implementing controls to lessen the chance or effect). Contingency planning, by contrast, is about having predefined actions to take if a risk event occurs, not about avoiding the risk in advance. It prepares for risk events and their triggers rather than preventing the risk from happening. The other options misstate these ideas: contingency planning is related to risk events, risk mitigation is not limited to transferring risk, and avoidance of risk entirely isn’t the aim of contingency planning.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy